Client: Rigid Paper, Rochdale, Lancashire
Job: Removal of Steam Boilerplant, Oil Tanks and Chimney
Scope of Work
Our team of engineers arrived on site, and began by carefully isolating the boilers from the oil supply. The interconnecting pipework, and ducting was then dismantled and removed from site, and the boilers readied for being skated out of the boilerhouse and lifted onto transport. A 250 tonne crane was then brought to site, with a 100 tonne crane alongside for the man-rider basket. The 250 tonne crane took hold of the chimney, while our engineers were lifted up to the ring of holding bolts, which were removed. The chimney was then lifted from the building and lowered to the ground.